Inward processing in Türkiye: extensions and closing The permit expires. The filing window opens.

Written by Efe Kamış · Co-founder
Published
Last updated
Basis Turkish Inward Processing Regime Decision and Communiqué (Export: 2006/12)
Reading 11 min

A Turkish inward processing authorisation certificate (DİİB) runs for up to 12 months depending on the sector and ends on the last day of the month in which it expires. Most applications for an extension, justified cause or force majeure must be made within 3 months after the certificate expires; an application made late is not considered. The same 3 months apply to closing the export commitment, and the administration sends no reminder. On top of this, the Ministry of Trade from time to time grants a general extension through a temporary article: the latest window opened on 17 April 2026 and runs for 6 months.

How the term is counted

Inward processing lets you import the inputs of a product you will export without paying customs duty. In return you give an export commitment, which must be met within a set period. The regime has two instruments:

Inward processing authorisation certificate (DİİB)
Issued by the Ministry of Trade; it allows duty-free imports and domestic purchases.
Inward processing permit (DİİZ)
Issued by the customs office; it covers imports only and is limited to the operations listed in the Communiqué (such as accessories, assembly, repair, packaging and precious metal work).

The term of the certificate or permit is set at up to 12 months depending on the sector. For shipbuilding, complete plants, products whose production takes longer than 12 months and defence products, the term may match the project (Communiqué art. 20/1–2).

The term starts on the date of the certificate. It ends not on the day the period runs out but on the last day of the month in which it expires, and any extensions, justified cause and force majeure periods count towards that date (Communiqué art. 20/3; Decision art. 10). A 12-month certificate issued on 15 March ends on 31 March of the following year.

Extension routes in one table

The Communiqué provides more than one extension route, each with its own condition, length and place of application. What they share: the application period starts once the certificate has expired, and there is no way back if it is missed (Communiqué art. 21/2, art. 23/2, art. 26/2).

Extension routes for an inward processing authorisation certificate
RouteCondition ExtensionApplication
Extension based on the first import The date of the first import is used; also applies if nothing was imported Up to 3 monthsWithin 3 months of expiry, to the Ministry (art. 21/1-a, art. 22/1)
Performance-based extension Exports made reach at least 25% of the commitment Half of the original termWithin 3 months of expiry, to the Ministry (art. 21/1-b, art. 22/2)
Justified cause Imports matching exports made in advance could not be completed Up to half of the original termWithin 3 months of expiry, to the Ministry (art. 23/1-a, art. 24/1)
Force majeure and extraordinary events Disaster, ban, war, epidemic, bankruptcy, strike and similar events occurring during the term According to the duration of the eventWithin 3 months of expiry, to the Ministry (art. 25, art. 26/1-a, art. 27)

For an inward processing permit (DİİZ) the application goes to the customs office and the periods differ: project-based extensions and justified cause and force majeure applications are made within 2 months of the permit's expiry (art. 21/1-ç, art. 23/1-b, art. 26/1-b). A justified cause extension on a permit requires production or exports of at least 25% of the commitment (art. 24/2).

The 2026 general extension window

The routes above are permanent. Beyond them, the Ministry can add a temporary article to the Communiqué granting a general extension to every open certificate issued before a given date. The latest window was published in the Official Gazette of 17 April 2026 and entered into force on publication (Communiqué, Export: 2026/2).

  • Scope: DİİB certificates and DİİZ permits issued before 17 April 2026 whose export commitment account has not yet been closed.
  • Condition: an application to the Ministry within 6 months of entry into force.
  • Extension: half of the original term of the certificate or permit, up to 3 months.
  • Exception: for permits covering goods under headings 7108, 7112.91 and 7113.19 (precious metals and jewellery) the extension is up to 1 month.

Two points to watch

The extension is not added to the old expiry date; it runs from the date the application is approved (temporary art. 37/6). Confirm the last day of the six-month application period with the Ministry, and do not leave the application to the final week.

This is not the first such window. A paragraph of this kind has been added to temporary article 37 of the Communiqué six times since 2023:

General extension windows opened under temporary article 37
Official GazetteScopeExtension
01.02.2023DİİB and DİİZ issued after 1 January 2020Not exceeding half of the original term
11.10.2023DİİB issued after 1 January 2020Not exceeding half of the original term
14.06.2024DİİZ issued after 1 January 2021 (precious metals excluded)Not exceeding half of the original term
28.12.2024DİİB and DİİZ issued after 1 January 2021 (precious metal permits excluded)Half of the original term, up to 3 months
11.09.2025DİİB and DİİZ issued after 1 January 2022 (precious metal permits excluded)Half of the original term, up to 3 months
17.04.2026No issue-date condition; precious metal permits in a separate paragraphUp to 3 months; up to 1 month for precious metal permits

Each paragraph gave a 6-month application period from its own entry into force. There is no commitment that another window will open; build your plan on the permanent routes.

Closing: three months after expiry

When the term ends the work is not over: the export commitment has to be closed. Under the Communiqué:

  • DİİB: within 3 months of the certificate's expiry at the latest, the information and documents in Annex 3 go to the regional directorate designated by the Ministry (art. 37/1-a).
  • DİİZ: within 3 months of the permit's expiry at the latest, the information and documents in Annex 4 go to the customs office (art. 37/1-b).

Keeping track of these periods is the company's responsibility; the administration sends no separate written notice (art. 37/2). If the documents are not submitted in time or turn out to be incomplete, the administration allows 1 month; if they are still not completed, the commitment is closed on the information and documents available (art. 38/1; Decision art. 19).

If the deadline passes

For goods brought in under the certificate, the formalities the regime requires can still be completed after the term ends, but the cost rises (Decision art. 22):

  • If they are completed within 1 month of expiry, they count as within the certificate, but twice the irregularity fine under Customs Law art. 241/3 is charged.
  • If they are completed within 2 months, they still count as within the certificate, but four times the irregularity fine is charged under art. 241/4.

This two-month tolerance does not replace an extension. If the commitment cannot be met within the term, the right move is to decide which extension route applies before the term runs out.

When it goes wrong

Nobody thinks about an extension before the certificate expires

The application period starts when the certificate expires and lasts 3 months (2 months for a permit). Once it has passed, the application is not considered (art. 21/2). When the export schedule slips, the first question is which route's condition is met: if 25% of the commitment has been exported, the performance extension; if the imports could not be completed, justified cause.

The general extension is assumed to be added to the old expiry date

In the 2026 window the extension runs from the date the application is approved (temporary art. 37/6). Plan the remaining time on a certificate whose term has already ended on that basis.

The company waits for a reminder before closing

The Communiqué rules this out explicitly: companies are not notified of the periods separately (art. 37/2). Three months spent with missing documents means the commitment is closed on the information at hand.

Three months are expected on a precious metal permit

In the 2026 window the extension for permits under headings 7108, 7112.91 and 7113.19 is at most 1 month (temporary art. 37/7). Expecting the same right from the same window leads to the permit running out early.

Frequently asked

What is the difference between a DİİB and a DİİZ?

The DİİB is issued by the Ministry of Trade and covers both imports and domestic purchases. The DİİZ is issued by the customs office, covers imports only and is limited to the operations listed in article 14 of the Communiqué. Where extension and closing applications go follows from this: the Ministry and the regional directorate for a DİİB, the customs office for a DİİZ.

Who can apply for the 2026 general extension?

Holders of DİİB certificates and DİİZ permits issued before 17 April 2026 whose export commitment account has not yet been closed. The application goes to the Ministry within 6 months of entry into force. The extension is half of the original term, up to 3 months; up to 1 month for precious metal permits (temporary art. 37/6–7).

Will the general extension open again?

Nobody knows. Paragraphs have been added to temporary article 37 six times since 2023, but that is neither a schedule nor a commitment. Build your plan on the permanent extension routes and the closing period.

On which day does the certificate expire?

Not on the day the period runs out but on the last day of the month in which it expires. Extensions granted count towards that date (Communiqué art. 20/3; Decision art. 10).

Sources

  1. Inward Processing Regime Communiqué (Export: 2006/12), consolidated text published by the Ministry of Trade (17.04.2026) Articles relied on: art. 3 (definitions of DİİB and DİİZ), art. 14 (operations eligible for a permit), art. 20 (term and expiry date), art. 21–22 (extension application and assessment), art. 23–24 (justified cause), art. 25–27 (force majeure and extraordinary events), art. 37–38 (closing), temporary art. 37 (general extension paragraphs; Official Gazette 01.02.2023, 11.10.2023, 14.06.2024, 28.12.2024, 11.09.2025, 17.04.2026) · ticaret.gov.tr · accessed 29 Sep 2026
  2. Official Gazette 17.04.2026 / 33227 — Communiqué amending the Inward Processing Regime Communiqué (Export: 2026/2) Paragraphs 6 and 7 added to temporary art. 37: application within 6 months, up to 3 months; up to 1 month for precious metal permits · resmigazete.gov.tr · accessed 29 Sep 2026
  3. Inward Processing Regime Decision no. 2005/8391, consolidated text published by the Ministry of Trade (16.08.2025) art. 10 (term; extensions set by communiqué), art. 19 (closing), art. 22 (formalities completed within 1 and 2 months of expiry: twice and four times the irregularity fine) · ticaret.gov.tr · accessed 29 Sep 2026
  4. Turkish Customs Law no. 4458 art. 108 (inward processing; suspension and drawback systems), art. 241/3–4 (irregularity fine) · mevzuat.gov.tr · accessed 29 Sep 2026

This page is for information only. It is not legal or customs brokerage advice. The Communiqué and the Decision were read directly and article numbers are given; which extension route is open for a particular certificate depends on its own terms and on the Ministry's assessment. Confirm the last day of the general extension application period and the application method with the Ministry of Trade or your customs broker. The irregularity fine is revalued every year, so no lira amount is given here.

Change log

  1. Page published. Terms, extension routes, the six paragraphs of temporary article 37 and the closing rules were read directly from the consolidated Communiqué and Decision published by the Ministry of Trade and from the Official Gazette of 17.04.2026. The last day of the general extension application period was not calculated and stated; confirming it with the Ministry is recommended.